The City of Rapid City is seeking a contractor to remove the pressure reducing valve (PRV) stations within the Spring Brook Acres Subdivision and replace approximately 6,200 ft of asbestos cement water main, as well as the affected service lines within the project limits. The project has an engineer's estimate of $2,210,000.00 and a base bid of $2,273,000.00. The contract was advertised with an authority of $2,210,000.00. Key aspects of the project include:
• Removal of PRV stations
• Replacement of 6,200 ft of asbestos cement water main
• Replacement of affected service lines
• Project limits within the Spring Brook Acres Subdivision
The project is expected to be completed within a certain duration, but the exact duration is not specified in the provided text.