The contract is for the modernization of the existing traction freight/service elevator at the District's Jackson Powerhouse in Snohomish County, Washington. The project requires all labor, equipment, tools, materials, permits, temporary facilities, and construction expertise to perform the modernization. The engineer's estimate for the project is $350,000.00. The contract was awarded to R. C. Zeigler Company, Inc. with a bid proposal of $449,734.00.
• The project includes modernization of the elevator to comply with applicable building codes.
• The contractor is required to provide all necessary labor, equipment, and materials.
• The project is located at the Jackson Powerhouse in Snohomish County, Washington.
• The engineer's estimate for the project is $350,000.00.
• The contract was awarded to R. C. Zeigler Company, Inc. with a bid proposal of $449,734.00.