The North Area Recovery Station Accessibility Improvements project involves the construction of improvements to the flow of traffic entering and exiting the North Area Recovery Station (NARS) site. The project includes asphalt paving, installing sidewalks and accessibility ramps, placing pavement striping, curb and gutters, and other items. The estimated construction cost is $1,300,000. The contract was awarded to Western Engineering Contractors, Inc.
• The project is located in Sacramento, California.
• The project includes various tasks such as mobilization, site preparation, demolition, and installation of asphalt, concrete, and other materials.
• The contractor is required to comply with all applicable laws and regulations, including those related to labor, safety, and environmental protection.
• The contract includes a bid guarantee and a payment bond to ensure the contractor's performance and payment of subcontractors and suppliers.