The City of Boise is seeking a contractor to resurface the Natatorium Pool basin, including sealing, tile, drains, and plaster. The contract was awarded to an unspecified vendor with a bid of $555,350.00. The project involves removal and resurfacing of the existing pool basin. The City of Boise reserves the right to reject any and all bids and to accept the bid that is in the best interest of the City.
• The scope of work includes removal and resurfacing of the existing Natatorium pool basin.
• The project requires a bid security in the form of a bid bond, certified check, cashier’s check, or cash in the amount of 5% of the bid amount.
• The City of Boise is an Equal Opportunity Employer.
• The contract will be awarded to the bidder who submits the lowest responsive bid.
• The project includes various line items, such as concrete, shotcrete, ceramic tile, plaster, equipment, mechanical, and electrical work.