Hemet Manufacturing Co., Inc. (dba Genesis Construction)
Raminha Construction, Inc.
Specialty Construction, Inc.
Description
The CSA-18 Settling Ponds - Liner Replacement Project is a construction project located in San Luis Obispo, CA. The project involves rebuilding the settling ponds, including extending the liner to the bottom of the pond and full-length of slopes. The existing clay liner will be used to the extent possible at the slopes and pond bottoms. The project also includes the removal of asphalt concrete pavement and the installation of new HDPE pipes. The engineer's estimate for the project is $142,050. The contract was awarded to multiple vendors, including Seamair Construction, Inc., R. Burke Corporation, Hemet Manufacturing Co., Inc. (dba Genesis Construction), Raminha Construction, Inc., and Specialty Construction, Inc. The key aspects of the project include:
• Rebuilding the settling ponds
• Extending the liner to the bottom of the pond and full-length of slopes
• Removing asphalt concrete pavement
• Installing new HDPE pipes
• The project is located in San Luis Obispo, CA
• The engineer's estimate for the project is $142,050
• The contract was awarded to multiple vendors