The 221st Pl SE Water Main Replacement Project involves the installation of approximately 1,064 lineal feet of 12-inch restrained joint DI water main, four fire hydrants, eleven water service replacements, and other related work. The project is located in a commercial business area and has an engineering estimate of $650,000. The contract was awarded to the apparent low bidder, Ponderosa Pacific Inc.
• The project includes the installation of 12-inch ductile iron pipe, 12-inch butterfly valves, 8-inch gate valves, 6-inch gate valves, fire hydrant assemblies, and other related work.
• The project also includes the abandonment of the existing 8-inch DI water main and the connection to an existing 12-inch water main.
• The contract has a bid schedule with various items and quantities listed.
• The project is expected to be completed within a certain timeframe, but the exact duration is not stated in the document.