The City of Corpus Christi is seeking a contractor to rehabilitate the Wesley E. Seale Dam Sluice Gate. The project involves the removal of three existing sluice gates and the installation of three new replacement gates. The contractor will be responsible for caring for the water during construction and ensuring that the municipal water supply is maintained at all times. The contract was awarded to the lowest bidder, H&S Constructors, with a total base bid of $349,000.
• The project includes the removal and installation of three new sluice gates
• The contractor is responsible for caring for the water during construction
• The municipal water supply must be maintained at all times
• The contract was awarded to H&S Constructors with a total base bid of $349,000
• The project also includes additive alternates for an electrician, dive team, and 250-ton crane and team