The contract is for the 2023/24 Pipe Rehabilitation – Pipe Burst & Open Cut project, which includes open cut and pipe bursting work. The project involves replacing existing sewer and storm drain lines with new ones. The contract was awarded to multiple vendors, including Enterprises Northwest, Inc., dba Earth Works Excavation, Emery & Sons Construction Group, LLC, and K & R Plumbing Construction Co., Inc. The contract has a total value of $945,974.50. The work includes open cut and pipe bursting of approximately 381 linear feet of existing 8-inch clay sewer and replacement with 10-inch HDPE pipe, as well as other work such as video inspecting, locating, and reconnecting sewer service and storm drain laterals.
• The project requires the prime contractor or subcontractor to have a minimum field experience for HDPE pipe bursting installation of three successfully completed projects totaling a minimum of 2,000 linear feet of mainline using the proposed pipe bursting technologies.
• The Engineering estimates for the project are Schedule ‘A’ - $194,000, Schedule ‘B’ - $182,000, Schedule ‘D’ - $322,000, Schedule ‘G’ - $113,000, and Schedule ‘H’ - $128,000.
• The contract encourages small, minority, and women-owned businesses to submit bids.
• The City of Corvallis is responsible for the project and has published the bid.