The contract is for the replacement of the Willett Drive Condensate Line and the reconstruction of the Law School Sanitary Sewer. The project includes excavation, bedding, and compaction for the extraction and replacement of the pipeline and sewer line. The estimated project completion date is August 24, 2019. The contract was awarded to Mechanical Systems, who bid $788,350.00 for the base bid and $79,409.00 for the bid alternate.
• The project requires the replacement of approximately 465 linear feet of sanitary sewer line.
• The project includes a pre-bid conference and a mandatory walk-through.
• The contract documents include a front-end document, drawings, and an addendum.
• The bid results are subject to review and acceptance by the University of Wyoming.