This contract is for the asphalt rehabilitation of R/W 10-28, replacement of concrete slabs, and T/W J shoulders at the Tampa International Airport. The project includes multiple phases of work, with specific black out dates and deadlines. The contract sum is approximately $13,986,577.73. The key aspects of this contract include the rehabilitation of the asphalt, replacement of concrete slabs, and the completion of the work within the specified timeframe. Some of the key features of the project include:
• The project is divided into multiple phases, with specific deadlines and black out dates.
• The contractor is required to complete all phases of work prior to moving on to the next phase.
• The contract includes provisions for changes to the contract sum and time.
• The contractor is required to provide all outstanding obligations to the owner under the contract, including close-out obligations, punch list items, warranty, and correction of defective and non-conforming work.