This contract is a county‑funded, public‑works project to replace a series of storm‑water‑management (SWM) culverts across Snohomish County, Washington. The work includes full site preparation, earthwork, drainage structure installation, roadway grading, pavement resurfacing, erosion control, and traffic‑control measures. The solicitation was advertised in February 2021, bids were due March 9 2021, and the contract was awarded to Konnerup Construction Inc on March 18 2021. The award is a lump‑sum, fixed‑price contract valued at roughly $1.77 million, based on the engineer’s estimate of $2.03 million.
• Scope: 78 line‑item BOQ covering mobilization, excavation, pipe and culvert installation (HDPE & concrete), back‑fill, asphalt paving, erosion‑control, traffic‑control, and ancillary items.
• Funding: Snohomish County Roads Funds; apprenticeship requirement of 15 % of the work.
• Procurement: Full and open competition with eight bidders; award to the lowest responsive bid (Konnerup).
• Requirements: 5 % bid bond, performance/pay bonds due within 20 days of award, certifications for debarment, wage‑payment compliance, and recycled‑material content.