The Industrial Court Wastewater Rehabilitation Project involves the rehabilitation of the Industrial Court Wastewater System. The project includes the replacement of approximately 346 linear feet of existing wastewater line, as well as the replacement of 3 manholes and 1,710 square feet of concrete pavement. The engineer's estimated budget for the project is $147,000.00. The contract was awarded through a competitive bidding process, with five vendors submitting bids. The bid tabulation sheet lists the bids received, but does not indicate which vendor was awarded the contract.
• The project involves the rehabilitation of the Industrial Court Wastewater System
• The project includes the replacement of approximately 346 linear feet of existing wastewater line
• The project includes the replacement of 3 manholes and 1,710 square feet of concrete pavement
• The engineer's estimated budget for the project is $147,000.00
• The contract was awarded through a competitive bidding process