The City of Rexburg awarded a municipal sanitary‑sewer construction contract for the North Yellowstone Sanitary Sewer Line (Project WW‑02‑25). The scope includes installing new gravity‑flow PVC sewer pipe (21‑in., 18‑in., and 12‑in.), constructing polymer manholes, trenching, back‑filling, de‑watering, surface restoration, a river crossing, and associated utility coordination and traffic control. The work is divided into Phase I (underground work completed by mid‑May 2025) and Phase II (substantial completion within 120 days of notice to proceed). The contract is a fixed‑price award to Edstrom Construction, Inc., with required performance and payment bonds equal to 100 % of the contract price and a $500 per day liquidated‑damage clause. Key contractual requirements include American Iron & Steel compliance, Davis‑Bacon prevailing‑wage rules, DBE participation, and Idaho public‑works licensing.