This contract is for the intersection improvements at Van Buren St & 152nd Dr, with a project number of 42061. The contract was awarded to TALIS Construction Corporation. The project involves the construction of traffic signal/intersection improvements, with a duration of 183 days. The contract includes a change order for a time adjustment, with a revised completion date of 10/31/2025. The contract also includes a certificate of liability insurance, with a policy period from 04/01/2025 to 04/01/2026. Some key points about this contract include:
• The contract is for a construction project, specifically intersection improvements.
• The project has a duration of 183 days.
• The contract includes a change order for a time adjustment.
• The contract has a certificate of liability insurance.
• The contract was awarded to TALIS Construction Corporation.