The contract is for the street resurfacing and reconstruction of Circle Boulevard (East of Hwy 99W) in Corvallis, Oregon. The work includes concrete street panel removal, excavation, and installation of base rock, as well as the installation of warm mix asphalt concrete pavement. The project also includes the reconstruction of ADA ramps, sidewalks, bike ramps, curb and gutter, and other work as shown on the plans. The engineering estimate for the project is $4,290,000.
• The project is a public works contract subject to ORS 279C.800 to 279C.870.
• The bid submission date was April 4, 2023, at 5:00 PM EDT.
• The bid posting date was March 2, 2023, at 9:32:43 AM EST.
• The City of Corvallis encourages small, minority- and women-owned businesses to bid.