The City of Rapid City has awarded a contract for the replacement of submersible pump equipment and electrical power distribution systems at Well #5 and Well #6. The contract includes the removal and replacement of existing equipment, as well as the installation of new electrical power distribution systems. The contract was awarded to Layne Water Resources, with a base bid of $221,900.00 for Well #5 and $221,300.00 for Well #6. The engineer's estimate for the project was $580,000.00.
• The contract includes the replacement of submersible pump equipment and electrical power distribution systems at two wells.
• The contract was awarded to Layne Water Resources.
• The base bid for Well #5 was $221,900.00, and the base bid for Well #6 was $221,300.00.
• The engineer's estimate for the project was $580,000.00.