The contract is for the replacement of culvert pipes in Units 23 and 56 of the City of Palm Bay. The project includes the removal, disposal, re-installation, and restoration of 45 cross drain culvert pipes. The contractor is required to provide all incidentals, including utility relocations, material furnishings, and restoration work. The contract was awarded to Hinterland Group for an amount of $567,489.00.
• The project is a turnkey project, meaning the contractor is responsible for all aspects of the project.
• The contractor is required to provide a 10% bid bond.
• The project includes the removal and disposal of existing culvert pipes.
• The contractor is required to restore the area to its original condition after completion of the project.
• The contract was awarded through a competitive bidding process.
• The City of Palm Bay is responsible for overseeing the project and ensuring its completion.