This contract is for the repair of the slope under the Granger Road Bridge in Bath Township, Ohio. The project involves the removal of undermined concrete slope protection and the replacement with grouted rock channel protection. The contract was awarded to Matt Winters Excavating, LLC for an amount not to exceed $174,000.00. The project has a fixed completion date of December 15, 2015.
• The project includes clearing and grubbing, concrete slope protection removal, pipe removal, rock channel protection, seeding and mulching, and erosion control.
• The contract was awarded through a competitive bidding process, with the Summit County Executive's Office serving as the contracting agency.
• The project is part of the County of Summit's Capital Improvement Program for 2015-2020.