The contract is for the NE 23rd St Sidewalk and 100th Ave NE & NE 24th St Intersection Improvements project. The work contemplated to be performed under this contract includes clearing and grubbing, removal of structures and obstructions, removal of asphalt pavement, removal of cement concrete curb, gutter, and sidewalk, construction of cement concrete curb, gutter, sidewalk, curb ramps, and driveway approaches, storm drainage improvements, installation of RRFB system, and property restoration and miscellaneous work. The contract was bid on by multiple vendors, with the lowest bid being $541,990 by an unnamed vendor, and the highest bid being $780,112 by Nordvind Company.
• The contract is for a public bid reading.
• The bid opening room is 1E-110.
• The project title is NE 23rd St Sidewalk and 100th Ave & NE 24th St Intersection Improvements.
• The project manager is Daniel Lam.
• The engineer's estimate for the total cost of the project is $648,994.