The Town of Southampton awarded a contract to replace a deteriorated shoreline bulkhead on Bay Avenue in East Quogue. The award went to South Shore Docks, Inc. for a corrected total of $322,915, with work required to be completed by the end of 2021. The project includes demolition of the existing structure, installation of a new bulkhead with I‑beam caps, pile driving, asphalt restoration, and associated safety features such as guardrails and ladders. The solicitation followed a full and open competitive process, receiving six bids, and the contract is funded from the town’s Bulkhead Repairs–Dams General Ledger account.
• Scope: Demolition, new bulkhead construction (255 LF), 37 piles, asphalt pavement restoration, guardrail and ladder installation.
• Budget: $322,915 (corrected total).
• Timeline: Bids closed 16 Jun 2021; award 15 Jul 2021; contract must be completed by 31 Dec 2021.
• Requirements: NY prevailing‑wage schedule PRC # 2021004490; 5 % bid security; fixed‑price lump‑sum contract.