Awarded vendors
- Northeast Earth Mechanics, LLC
Description
This contract concerns the replacement of two existing culverts on Franklin Street over Horne Brook in Derry, NH, including associated water and sewer line work and a short roadway reconstruction. The work is to be performed on a unit‑price basis, with an estimated total project value near $700 k. The town required bidders to be pre‑qualified under the New Hampshire Department of Transportation classifications and to submit electronic bids via QuestCDN. Northeast Earth Mechanics, LLC was awarded the contract.
• Scope: install a precast concrete box culvert (8 ft × 6 ft × 56 ft), replace water and sewer mains, and reconstruct ~140 ft of roadway.
• Schedule: construction to start mid‑June 2024 and finish by late August 2024.
• Procurement: sealed electronic bids, unit‑price pricing, full open competition, no set‑aside restrictions.
• Requirements: NHDOT pre‑qualification, bid security, $50 document‑download fee, and adherence to the town’s erosion‑control and traffic‑management plans.