The contract is for the construction of the 143rd Street and S. Locust Street Storm Drainage Improvement project. The work consists of modifying an existing RCB, sanitary sewer relocation, roadway replacement, storm sewer improvements, home demolition, and site grading. The contract was awarded to Linaweaver Construction, Inc. for $516,809.00. The project involves various tasks such as mobilization, grading, clearing and grubing, erosion control, traffic control, house demolition, and removal and replacement of existing asphalt pavement, sidewalk, and concrete curb and gutter.
• The project requires the contractor to furnish and pay for satisfactory performance and payment bonds.
• The City of Olathe reserves the right to reject any or all bids or to waive any informality in the bidding.
• The contract award amount is $516,809.00.
• The contract was awarded on May 21, 2013.