The contract is for the replacement of the roof at the Osborn Aquatic Center Pump Room. The work consists of providing all services, labor, materials, equipment, and permits necessary for the installation of a Thermoplastic Polyvinyl Chloride (PVC) Fleeceback 60mil Membrane Roofing system. The contract was awarded to five different vendors, with bids ranging from $22,440 to $64,500. The contract is a lump sum contract, with the scope of work including cleaning the existing roof, adhering 60 mil PVC to the existing roof system, and reusing flashing, coping, and metal.
* The contract is for a specific project with a clear scope of work
* The contract is a lump sum contract, which means that the vendor is paid a fixed amount for the completion of the project
* The contract has a specific timeline, with the bid opening date and time listed as 8/31/2023 10:00 AM
* The contract has a specific location, with the project taking place at the Osborn Aquatic Center Pump Room in Corvallis, Oregon