The 24K: 6400 West & 3100 South Anderson Line Repair Project involves replacing a 24-inch concrete lined steel pipe and installing 89 feet of new 30-inch HDPE DR 11, as well as installing new services on the existing Asbestos Cement pipe in West Valley. The project requires obtaining permits, project supervision, mobilization, demolition, and removal of existing water lines. The contract has a base bid schedule and a bid alternate schedule. The engineers' estimate for the project is $500,000.00.
• The project includes installing a new water line, residential services, air release valves, and valves.
• The contract has a lump sum payment structure.
• The project requires coordination, cement treated fill, and asphalt pavement removal.
• The contract has a bid tabulation section that lists the bids from different companies.