This contract concerns a comprehensive power‑generation and cooling‑system upgrade at the South Brooklyn Hospital campus, a NYC Health + Hospitals facility. The scope includes replacement of existing electrical distribution panels, installation of new UPS and emergency‑power panels, addition of a 1600 A automatic transfer switch, replacement of fan‑coil units with redundant chilled‑water systems, and upgrading the fire‑sprinkler network to meet current code. The work is to be performed under a lump‑sum, design‑build arrangement, with a 450‑day performance period, extensive M/WBE participation (25 % minimum), and strict compliance with NYC building, mechanical, and fire codes.
• Electrical: New panelboards, ATS, UPS tie‑ins, conduit, and emergency‑power distribution.
• Mechanical/HVAC: Redundant wall‑mounted fan‑coil units, chilled‑water piping, condensate pumps, VFD‑controlled fans, and associated controls.
• Fire‑Protection: Replacement and augmentation of sprinkler heads throughout IT spaces.
• Administrative: Requires full PLA compliance, 25 % M/WBE utilization, 10 % bid bond, 100 % performance bond, and detailed documentation (as‑built, warranties, O&M manuals).