The contract is for the supply of asphaltic concrete materials, including 301 Asphalt Virgin Materials, 301 Asphalt With Recycled Asphalt Product (RAP), and 448-2 Intermediate Course Asphalt. The contract was awarded to two vendors, Allied - The Shelly Co. and Kokosing Materials, Inc. The contract period is from January 1, 2017 to December 31, 2017. The contract includes various items, such as asphalt materials, tack coat, and buckets. The prices for each item are listed in the contract document.
• The contract includes a list of items with corresponding prices, such as $49.75 per ton for 301 Asphalt Virgin Materials and $59.75 per ton for 448-2 Intermediate Course Asphalt.
• The contract has a minimum ton requirement of 18 tons for Allied - The Shelly Co.
• The contract includes a delivery cost of $79.00 per hour for Allied - The Shelly Co.
• The contract has a contract number of 20170005 for Allied - The Shelly Co. and 20170006 for Kokosing Materials, Inc.