The contract is for the 2025 Hot Mix Asphalt Paving project, which includes full depth reclamation of existing pavement, milling of existing pavement, placement of hot mix asphalt base and surface courses, and other related work. The project requires bidders to be pre-qualified by the Carroll County Department of Public Works prior to bid opening. The contract was awarded to M.T. Laney Co., Inc. for a total amount of $4,151,560.60.
• The project involves construction of driveway tie-ins, adjusting and rebuilding of inlets, manholes, and valve boxes, and installing new storm drain pipes and inlets.
• The project requires maintenance of traffic and all incidental work as indicated in the specifications or special provisions.
• The contract was awarded on August 14, 2025, at 11:32 a.m. EST.
• The contract documents, including the bid tabulation and contract award, are available for download.