The City of Dothan Utilities awarded a contract for the procurement of 3‑phase pad‑mount transformers (150 kVA and 300 kVA) to Gresco Utility Supply Inc. The bid process was open competition, with the award determined by the lowest evaluated cost under a 5 % rule. Five units of each rating are to be supplied, with lead times of 26‑30 weeks after drawing approval. The total contract value is estimated at roughly $300,000, and the award was formalized on 21 February 2023.
• Scope: Supply of 5 × 150 kVA and 5 × 300 kVA pad‑mount transformers (7.62‑13.2 kV primary, 120/208 V secondary).
• Procurement: Full and open competition; award based on evaluated cost; firm‑fixed‑price arrangement.
• Timeline: Bids closed 14 Feb 2023, award 21 Feb 2023, vendor lead time ~6‑7 months post‑drawing approval.