This contract awards a single‑vendor, stipulated‑sum demolition project for a wood‑framed nuisance structure at 56 S. Lafayette Street, Mobile, AL. The scope requires wet‑method demolition, complete removal of footings, slabs, utilities, and debris, compliance with lead‑based paint and asbestos handling procedures, extensive erosion‑ and sediment‑control measures, and final site restoration through seeding and mulching. The City mandates a current Mobile business license, all required permits at no cost to the contractor, and submission of detailed payment and lien‑release documentation. Liquidated damages of $250 per day apply if the work exceeds 15 days beyond the stipulated substantial‑completion date.
• Wet‑method demolition with hazardous‑material (LBP/Asbestos) controls
• Full utility disconnection, site clearing, and BMP‑based erosion control
• Post‑demolition site stabilization (topsoil, seed, mulch) and required close‑out documentation