The contract is for interior painting services for Martin Hall at Eastern Kentucky University. The project includes furnishing all labor, materials, equipment, and services necessary to complete the work outlined in the event and attachments. The engineer's estimate for the project is $400,000.00. The contract has three line items: Martin Hall Interior Painting, Alternate One (painting doorframes), and Alternate Two (painting hard ceilings). The contract was awarded to five vendors: Winners Circle Painting LLC, Ideal Painting LLC, Wilson Painting Company LLC, CPPL, LLC, and True Colors LLC.
• The contract has a substantial completion date of 40 days from the start date and a final completion date of 43 days from the start date.
• The contract has liquidated damages of $200 per day until substantial completion and $100 per day until final completion.
• The contract requires bid bonds and performance bonds unless otherwise stated.
• The contract has a mandatory pre-bid meeting and a bid submission deadline.
• The contract has a list of prerequisites that bidders must review and complete before submitting a bid.