This contract is for the painting of water storage tanks in the City of Edgewater, Florida. The contract was awarded to Shamrock Restoration Services Inc for a total amount of $77,636.00. The contract duration is 90 days, and the work is expected to be completed by July 2, 2021. The contract includes provisions for payment, retainage, and termination, as well as requirements for the contractor to provide labor, materials, and equipment.
• The contract price is $77,636.00
• The contract duration is 90 days
• The work is expected to be completed by July 2, 2021
• The contractor is responsible for providing labor, materials, and equipment
• The contract includes provisions for payment, retainage, and termination