This contract is for the North P Street Culvert Extension project, which involves removing an existing dual 42" corrugated metal pipe and installing approximately 35 feet of dual 10' x 8' box culverts, as well as constructing a concrete wingwall and transition structure. The project was awarded to Paskey Inc. for $231,737.93. Key aspects of the project include:
• Removal of existing corrugated metal pipe
• Installation of new box culverts
• Construction of concrete wingwall and transition structure
• Award amount: $231,737.93