The Hopkinton Public Schools Adaptive Playground contract awards the design‑build construction of a fully ADA‑compliant playground at Marathon Elementary School. The scope includes site clearing, grading, utility coordination, concrete footings and pads, poured‑in‑place polyurethane safety surfacing, installation of playground equipment, shade structure, chain‑link fencing, lighting, landscaping, and associated erosion‑control measures. The project follows strict federal, state, and local regulations (ADA, Mass. Architectural Access Board, MassDOT, OSHA) and requires the contractor to obtain all necessary permits, post performance bonds, and manage a comprehensive construction schedule culminating in substantial completion by late September 2026.
• Comprehensive civil works: earth‑moving, grading, utility protection, and concrete foundations.
• Full playground build‑out: safety surfacing, equipment installation, shade structure, fencing, lighting, and landscaping.
• Regulatory compliance: ADA, Mass. building code, M‑DEP erosion controls, and mandatory inspections.