The contract is for the reconstruction of the gas collection and control system at the Neal Road Recycling and Waste Facility. The project involves the removal of damaged landfill gas collection components, minor excavation, minor placement of fills, landfill gas well repairs and/or replacement, vadose zone well repair and/or replacement, installation of a condensate sump, installation of HDPE landfill gas headers, laterals, fittings, and valves. The engineer's estimate for the project is approximately $921,000.00.
• The project is located at the Neal Road Recycling and Waste Facility.
• The project involves the reconstruction of the gas collection and control system.
• The engineer's estimate for the project is approximately $921,000.00.
• The project was advertised on January 18, 2019, and bids were opened on February 8, 2019.
• A mandatory pre-bid meeting was held on January 31, 2019.
• The project is expected to be completed within a certain timeframe, but the exact duration is not specified.
• The contract was awarded to one of the six bidders, but the exact vendor is not specified.