This contract is for the renovation of the basement at Linn Education Center, which includes removing and replacing existing electrical, lighting, plumbing, and exhaust fans, as well as installing new resin surfaces and replacing toilet partitions. The contract was awarded to JP Construction, LLC for a total bid of $38,550.00. The project is expected to be completed 5-7 weeks after approved submittals.
• The renovation includes work on the lower floor men's and women's restrooms
• The project requires the removal and replacement of existing electrical, lighting, plumbing, and exhaust fans
• The contractor must install a new 3/16" troweled resin surface and 4" resin coved wall base in the restrooms
• The existing toilet partitions must be removed and replaced
• The contractor must clean and paint the existing ceiling grid members