The 2025 Allendale Fish Screen Improvements project involves modifications and replacements to the Allendale Fish Screen in Granite County, Montana. The project includes work such as modifying and replacing end idler sprockets and brackets, replacing linear rail bearings, fabricating and installing porosity baffles, and fabricating and installing brush kickout blocks. The contract was awarded to Moreaux Contracting LLC and Princeton Planning & Project Management, PLLC. Key aspects of the project include:
• Modification and replacement of the two end idler sprockets and brackets
• Replacement of the linear rail bearings on the brush carriage
• Fabrication and installation of 12 porosity baffles (24 total plates) with stiffeners
• Fabrication and installation of three brush kickout blocks
• Project schedule: completion of all work prior to June 6, 2025, is desired
• Mandatory pre-bid conference and project walk-through held on May 7, 2025
• Lowest bid from responsive and responsible bidders will be selected