This contract is for the mechanical and electrical upgrades at the Eagle Valley Center. The project includes the replacement of the existing oil boiler and tank with a new electric hydronic heating system, domestic water upgrades, and electrical system upgrades. The contract was awarded to Carver Construction, LLC. for a total bid of $395,580. The project is expected to commence in February 2024 and be completed eight weeks later.
• The contract includes the replacement of the existing oil boiler and tank with a new electric hydronic heating system.
• The project includes domestic water upgrades with a dedicated electric water heater.
• The electrical system will be upgraded, including a new buried service and main distribution panel.
• The project is expected to commence in February 2024 and be completed eight weeks later.
• The contract was awarded to Carver Construction, LLC. for a total bid of $395,580.