The City of Spokane awarded a contract for the off‑site fabrication of three stainless‑steel mounting components (Skirt Base Mount, Mounting Bracket, and Rubber Clamp) based on engineering drawings C‑1000‑09‑0002, C‑1000‑09‑0003, and C‑1000‑09‑0004. Naimor inc was the lowest‑priced bidder and received the award. The contract is priced on a unit‑price basis (prices exclude tax, freight included), with a 9% tax applied to the subtotal. The award includes a lead time of 30 days for delivery of the fabricated items.
• Scope: Fabricate stainless‑steel mounts per detailed GD&T drawings; quantities are for comparison only—payment is made for actual delivered units.
• Pricing: Unit pricing provided; total awarded base price $12,029.68 plus $1,082.67 tax = $13,112.35.
• Requirements: Must meet ANSI/ASME Y14.5 tolerances, deburr edges, mask threaded/precision holes before any coating; freight is included in unit price.
• Evaluation: Awarded on lowest total cost with consideration of lead‑time; competition was open (RFQ).