The contract is for the North Fork of the Powder/Crazy Billy Mine Timber Stand Improvement project, which involves timber stand improvement on 73 acres and 21.50 acres of land. The project is expected to be completed by September 15, 2016. The contract was awarded to three vendors: Mountain Man Wood Projects, LLC, Powers Logging, and Summitt Forests, Inc. The total value of the contract is $141,750.00, $27,877.50, and $28,828.00 respectively.
• The project involves timber stand improvement on 73 acres and 21.50 acres of land.
• The contract was awarded to three vendors: Mountain Man Wood Projects, LLC, Powers Logging, and Summitt Forests, Inc.
• The total value of the contract is $141,750.00, $27,877.50, and $28,828.00 respectively.
• The project is expected to be completed by September 15, 2016.
• The contract has a duration of 14 days per contract.