This contract awards the renovation of an open area on the 3rd‑floor of the Outagamie County Justice Center into three new offices (approximately 617 sf). The work includes selective demolition, installation of hollow‑metal doors, fire‑rated overhead coiling doors, fire curtains, gypsum board walls, tile‑carpet flooring, interior paint, and associated electrical, HVAC, and life‑safety systems. All work must comply with strict noise‑restriction windows (no hammer‑drilling during court hours), background‑check requirements for personnel, and secure tool/material handling. The contract is a lump‑sum, competitive sealed‑bid award to RJM Construction for a bid amount of $72,400, with performance and payment bonds equal to the contract sum and a 5 % bid bond. Substantial completion is required by 19 Dec 2025, with liquidated damages of $100 per day thereafter.