This contract calls for the complete demolition of an abandoned structure at 1101 S. Broad St, Mobile, AL, including wet‑demolition, utility disconnections, site clean‑up, erosion and sediment control, lead‑based paint/asbestos handling, and post‑demolition seeding/landscaping. The City of Mobile’s Municipal Enforcement Department issued a sealed‑envelope RFQ (ME‑021‑22) with a quote deadline of March 2 2023. The award went to Thomas and Sons Contracting, LLC. The contractor must finish the work within 15 calendar days after receiving a Notice to Proceed, with liquidated‑damages of $250 per day for any delay beyond an additional 15‑day grace period. Additional requirements include E‑Verify enrollment, proof of insurance, AIA forms, and a final newspaper notice of completion.
• Wet demolition of the entire structure (including footings, slabs, CMU piers).
• Mandatory utility capping (sewer, water, gas) and compliance with lead‑asbestos disposal regulations.
• Required erosion‑control BMPs, permanent site stabilization, and post‑demolition seeding.
• Fixed‑price contract with strict 15‑day completion timeline and $250/day liquidated‑damage clause.