Awarded vendors
- JWC Environmental Inc.
Description
The Four Rivers Sanitation Authority (FRSA) solicited bids for the procurement of two complete municipal wastewater grinding/shredding systems, associated control panels, emergency‑stop units, and related accessories for the Snow Avenue Pump Station in Loves Park, Illinois. The contract is a sealed‑envelope bid with a 5 % bid security, requires a performance bond (added by Addendum 1), prevailing‑wage compliance, ISO 9001 certification, extensive insurance coverage, and a two‑year warranty. Payment is structured in three milestones (5 % on shop‑drawing approval, 70 % on delivery, 25 % on start‑up and acceptance). The award was made to JWC Environmental Inc., and the bid deadline and opening were both on July 15, 2024 at 10:00 a.m. CDT.
• Equipment: Two 460 V, 3‑phase wastewater grinder units (capacity 12.8 MGD) with dual‑shaft, steel cutter stacks, screen drums, and stainless‑steel NEMA 4X control enclosure.
• Mandatory requirements: 5 % bid bond, performance bond (100 % of annual contract price), prevailing‑wage compliance, ISO 9001, insurance limits (General Liability $1 M, Auto $1 M, Employers’ Liability $500 k, Umbrella $2 M), and a two‑year warranty.
• Schedule & payment: Bid due July 15 2024; 5 % on shop‑drawing approval, 70 % on delivery, 25 % on successful start‑up; warranty starts after completion; delivery hours 7:30 a.m.–3:00 p.m. M‑F to 3333 Kishwaukee St., Rockford, IL.