The City of Port St. Lucie has awarded a contract to JMT - Johnson, Mirmiran & Thompson, Inc. for the provision of Construction Engineering and Inspection (CEI) services for the St. Lucie West Blvd. and Peacock Blvd. Intersection Improvement project. The contract has a duration of 180 days and a total value of $409,602. The scope of work includes constructability review, on-site inspections, sampling and testing, engineering services, and project meetings. The Consultant will be required to maintain complete and accurate records of activities, meetings, and events related to the project, and will be responsible for ensuring that all work is performed in accordance with the contract requirements and applicable laws and regulations.
• The contract includes a provision for the Consultant to provide a Constructability Review Package, which will include a review of the project plans and technical specifications to ensure that work requirements are clear and all documents are coordinated.
• The Consultant will be required to perform on-site inspections to monitor the Contractor's construction activities and ensure compliance with the plans, specifications, and special provisions.
• The Consultant will be responsible for reviewing and responding to Contractor Requests for Information (RFIs) and providing recommendations to the City for any change orders necessary to complete the project.
• The Consultant will be required to maintain detailed records of the project, including daily work reports, sampling and testing results, and documentation of all project meetings and events.
• The contract includes provisions for termination, including termination for convenience, termination for non-appropriation, and termination for default.
• The contract requires the Consultant to maintain insurance coverage, including workers' compensation, commercial general liability, and professional liability insurance.