The 2019 Concrete Pavement Repair Program for Summit County is a contract for the repair of concrete pavements in various townships and cities within the county. The scope of work includes saw cutting, removing concrete slabs, excavating sub-grade, backfilling with Item 304, and pouring new concrete slabs, among other tasks. The contract has a completion date of September 15, 2019, and an engineer's estimate of $489,175.00. The contract was awarded to multiple vendors, including Perrin Asphalt Company, Tri Mor Corp, Daniel A Terreri & Sons, Inc., Lockhart Concrete Co, karvo Companies Inc., Liberta Construction, and Spano Brothers Construction, Inc.
• The contract involves the repair of concrete pavements in various locations, including Bath Township, Copley Township, City of Green, Sagamore Hills Township, and Twinsburg Township.
• The scope of work includes a range of tasks, such as saw cutting, removing concrete slabs, excavating sub-grade, and backfilling with Item 304.
• The contract has a completion date of September 15, 2019, and an engineer's estimate of $489,175.00.
• The contract was awarded to multiple vendors, with each vendor providing a detailed bid for the work to be performed.
• The contract includes a range of line items, including concrete pavement repair, curb repair, sidewalk repair, and traffic maintenance.