This contract concerns the demolition and full site remediation of a nuisance property at 414 Gaston Street, Mobile, AL. The City of Mobile’s Municipal Enforcement Department issued an RFQ (ME‑183‑22) seeking a single total‑price quote for wet demolition, utility disconnections, hazardous‑material handling, erosion control, debris removal, and post‑demolition site stabilization. The award was later recorded as being given to AA&A Demolition. The work must be completed within 15 calendar days of a notice to proceed, with strict liquidated‑damage penalties for delays and extensive documentation requirements for environmental compliance and final close‑out.
• Scope includes wet demolition of structures, removal of footings, slabs, CMU, and all vegetation ≤ 8 in., plus proper handling of lead‑paint/asbestos and disposal at a permitted landfill.
• Contractor must provide proof of E‑Verify enrollment, city‑required insurance, signed AIA payment forms, and post‑completion newspaper notice, as well as affidavits of lien releases.
• Performance schedule is 15 days; liquidated damages of $250 per day apply for any overruns, and stringent erosion‑control standards must be met under federal, state, and local regulations.