The City of Keene is seeking a contractor to replace the aeration pipe at the wastewater treatment facility. The project involves the discontinuance of the existing 16" ductile iron line and the installation of a new 16" stainless steel aeration line, fittings, and valves. The contract was awarded to N.A. Manosh, Inc for a total of $391,000.00. The project is funded by the City of Keene's FY20 CIP Budget.
• The project involves the replacement of the aeration pipe at the wastewater treatment facility.
• The contract was awarded to N.A. Manosh, Inc for a total of $391,000.00.
• The project is funded by the City of Keene's FY20 CIP Budget.
• The contract details, including the bid amount and any addenda, are provided in the project summary document.