The 2017 Out of the Dust project involves the asphalt paving of alleys or streets at various locations throughout Rapid City. The project has an advertising authority of $100,000.00. The contract was awarded to multiple vendors, including G.T.1, Companies, J&J Asphalt, Western Construction, and Hills Materials. The bid results show the base bid and alternative bid prices for each vendor.
• The project is an annual Out of the Dust Project.
• The bid posting date was September 9, 2017, and the bid submission date was September 26, 2017.
• A pre-bid conference was held on September 19, 2017.
• The bid results include the engineer's estimate, base bid, and alternative bid prices for each vendor.