This contract awards Cardinal Construction the renovation of two bathing suites at Brewster Village, Appleton, WI, encompassing complete demolition, waterproofing, tile installation, ceiling acoustic tile replacement, gypsum board work, and associated mechanical, electrical, and plumbing coordination. The project is governed by an AIA A101‑2017 lump‑sum agreement with a 5 % bid bond and performance/payment bonds equal to the contract sum, and includes liquidated damages of $100 per day for late substantial completion.
• Scope: Tile and ceiling replacement, selective demolition, waterproof membrane, backer‑board, gypsum board, plumbing fixtures, and related finish work for two suites.
• Schedule: Work must start July 22 2026, achieve substantial completion by November 13 2026, and final completion by November 23 2026.
• Procurement: Competitive sealed‑bid process (full and open competition) with a bid deadline of July 8 2026; winning bid amount $98,553.