This contract concerns the full resurfacing of Grant Avenue (CR‑283) from East 49th St. to East 71st St., spanning the City of Cleveland and the Village of Cuyahoga Heights. The work includes removing existing pavement, preparing the base, and installing new asphalt or equivalent surface to meet ODOT standards, with all labor, materials, equipment, and related services required for completion. The project is limited to ODOT‑pre‑qualified contractors, carries a bid guarantee of 10 % of the total bid, and requires performance and payment bonds naming ODOT as obligee. The contract value is approximately $1.58 million, with a firm‑fixed‑price arrangement and a completion deadline of 15 Nov 2024.
• Scope: Complete roadway resurfacing (≈22 blocks) including demolition, base preparation, and new surface placement.
• Eligibility: Only ODOT‑pre‑qualified firms; bid guaranty of $163,444 (10 %).
• Schedule: Bids due 20 Feb 2024; work to be finished by 15 Nov 2024 (≈9 months).