The contract is for the construction of the Ralston Road Bridge at Vekol Wash in Pinal County, Arizona. The contract was awarded to Sunland Asphalt & Construction, LLC, for a lump sum amount of $7,968,507.00. The project is expected to be completed within 365 calendar days. The contract includes provisions for installment progress payments, retention, and final payment. The contract also includes provisions for claim resolution, governing law, and venue. Key aspects of the contract include:
• The contract is for a fixed price of $7,968,507.00
• The project is expected to be completed within 365 calendar days
• The contract includes provisions for installment progress payments and retention
• The contract includes provisions for claim resolution, governing law, and venue
• The contract was awarded to Sunland Asphalt & Construction, LLC, a corporation